问答题 【问题2】 分别按照非典型偏差和典型偏差的计算方式,计算项目在第13周末的完工尚需成本(ETC)和完工估算成本(EAC)
问答题 【问题1】 请计算当前的成本偏差(CV)和进度偏差(SV),以及进度绩效指数(SPI)和成本绩效指数(CPI),并分析项目的进展情况。
单项选择题 Your company CEO just sent you an E-mail asking you to make a … on your project , which has been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend. The first step in preparing the presentation is to ( ).